At the October 22 Lacey Township Committee meeting, a resident at the public microphone asked a procedural question. Why had the draft ordinance prohibiting data centers gone to the Planning Board for November instead of October? The answer, recorded in the meeting video, was a deadline. The township had missed the Planning Board's agenda cutoff ahead of that board's October 19 meeting, so the draft will be taken up in November.

Small reasons like that shape the local side of the Oyster Creek story. Federal regulators, Trenton and Holtec are each moving on their own schedules. In Lacey itself, the item with a date on the calendar is a zoning ordinance that hasn't had a first reading. If adopted, it would put in writing something township zoning already does.

The Data-Center Question Started West of the Parkway

Data centers first came before the Township Committee on May 28. According to the township's minutes, that discussion was informational, focused at first on Pinelands properties west of the Garden State Parkway, and was tabled for research with no action taken. NJ.com's June 5 report also described the May discussion as limited to the Pinelands question west of the Parkway. At that same meeting, Mayor Steven Kennis said no application or proposal for a data center had been submitted for the Oyster Creek property and that decommissioning was still underway.

On July 30, Holtec's announcement about the former plant tied the two subjects together. The company said the Oyster Creek site is "planned to feature four SMR-300 units" with a combined capacity of 1,360 MWe. It listed the "potential integration of AI data centers" among the expected benefits. The same post includes a forward-looking-statements caution that covers both the reactors and the data-center language.

So a debate that began over Pinelands parcels ended up attached to the bayside brownfield on Route 9. That explains why the draft ordinance covers every zoning district.

Each Layer Is at a Different Stage

Conversations about Oyster Creek tend to treat decommissioning, state law, Holtec's reactor plan and the data-center ordinance as one story. Each sits with a different decision-maker and is at a different stage.

Item Who decides Where it stands in late October 2026
Decommissioning and site cleanup U.S. Nuclear Regulatory Commission License Termination Plan approved; Holtec says dismantlement is more than halfway complete
Site release and license end U.S. Nuclear Regulatory Commission NRC estimates partial site release in 2029, excluding spent-fuel storage, and license termination by the end of 2035
State nuclear permitting State of New Jersey S3870/A4528 signed April 8, 2026
New nuclear procurement BPU and NJEDA under the Power NJ Act Signed July 13, 2026; covers at least 1,100 MW statewide and doesn't approve Oyster Creek
Four SMR-300 units at Oyster Creek Holtec, then regulators Proposed; NRC lists Holtec's SMR-300 work as pre-application activity
Statewide data-center moratorium State of New Jersey Lacey adopted Resolution #2026-280 on Sept. 10 supporting one
Lacey's data-center ban ordinance Planning Board review, then Township Committee Drafted and referred, but not introduced

The state laws cleared the way for new nuclear projects in general without approving any particular one. According to the governor's April 8 release, S3870/A4528 amended the Coastal Area Facility Review Act so the Department of Environmental Protection may approve nuclear-facility permits when radioactive-waste storage is safe and meets NRC standards. The Power NJ Act created a competitive procurement process for new nuclear generation.

The timeline for Holtec's reactors is still loose. POWER magazine reported a 2036 target for commercial operation, drawn from a July 10 Holtec securities filing, and noted that no construction-permit schedule had been disclosed. On August 5, the American Nuclear Society reported that Holtec had not publicly announced an Oyster Creek timeline. The NRC's construction-permit filing for Holtec's reactor design is for Pioneer Units 1 and 2 at Palisades in Michigan. On the local side, the Sept. 10 minutes record committee members saying Holtec had not contacted them about an SMR.

Zoning Already Leaves Data Centers Out

The township's Aug. 13 meeting minutes show why the draft ordinance may change less than its title suggests. Committeeman Dave Laureigh said he doesn't support data centers and noted they aren't a permitted use in the township. According to those minutes, Mr. Connors advised the township to keep watching state legislation, because changes in state law could affect what municipalities are allowed to regulate.

Committeewoman PeggySue Juliano made a related point in the same discussion. Even if Lacey adopted a specific prohibition, she said, future state legislation could supersede local rules.

Two months later, Juliano was the one who put a draft ban forward. According to the Oct. 8 minutes, she said she had asked the township attorney to prepare an ordinance prohibiting data centers in all zoning districts. She recommended sending it to the Planning Board because it would amend the township's zoning regulations, and the governing body agreed to forward it for the board's November meeting.

The committee isn't of one mind on the subject. On Aug. 13, Committeeman Peter Curatolo said that, hypothetically, a properly located facility in an industrial area could benefit the township financially through a host community benefit agreement. He stressed that he was not expressing support for data centers and that they are not a permitted use. Patch's Sept. 11 coverage of the moratorium resolution reported that residents pressed for a local ordinance and that Curatolo argued a small facility near the nuclear plant might have little noticeable effect.

According to the Sept. 10 minutes, that resolution, #2026-280, was a statement of support. It backs a temporary statewide moratorium on approving and developing new large-scale data centers until New Jersey sets comprehensive standards and towns have had time to review their own land use rules. It doesn't create a moratorium in Lacey or anywhere else.

How the Draft Becomes a Vote

At the Oct. 22 meeting, an official explained why the formal review clock hasn't started:

"There is no 35day clock start because we did not introduce it here at this level. So, they got it in advance to make any changes or suggestions to the ordinance um prior to us introducing it."

Based on what officials described at the October meetings, these are the steps:

  1. Planning Board review. The board is scheduled to meet Monday, Nov. 16, 2026, at 6:30 p.m. at Town Hall, 818 W Lacey Road, Forked River. Officials said on Oct. 22 that the draft will be on its November agenda. As of late October, the board's newest posted agenda in the township's Agenda Center was for Oct. 19.
  2. Suggested changes come back. Because the board is seeing the draft before introduction, its comments can be folded in before the committee formally acts.
  3. Introduction at the Township Committee. The ordinance would then get its first reading. Officials said that once an ordinance has been introduced, the Planning Board's 35-day review window applies.

Later in the same meeting, an official said the draft was now with the Planning Board. That official also gave the view that current zoning already bars data centers as permitted uses.

What Else Is Still Unresolved at the Site

Data centers aren't the only open Oyster Creek question in Lacey. Taxes on the spent-fuel storage casks are still in dispute. In a Feb. 25, 2025 decision, the New Jersey Tax Court held that the casks are taxable as real property, in appeals covering tax years 2018 through 2024. At the Oct. 22 meeting, an official said the appeal remains in court.

The reactor proposal is on a far longer schedule. On Aug. 13, Laureigh said any redevelopment of the Oyster Creek property is still many years away. The NRC's own estimates have the license ending around the end of 2035. As of the Sept. 24 minutes, Mayor Kennis had confirmed that the township had received no data-center application.

For Lacey and Forked River residents, the next fixed public date in all of this is the Planning Board session on Nov. 16. The township posts its agendas, minutes and meeting recordings in its Agenda Center.

This post is general information about public proceedings, not legal advice. If a zoning question affects your own property, confirm the details with a land use attorney or the township.

If you own in Lacey or Forked River and want to talk through how Oyster Creek's long timeline fits your own plans, Camille Simms follows these township meetings closely and is glad to walk you through it. Request your free home estimate and marketing plan whenever you're ready.

Work With Camille

Whether you’re launching a new initiative or seeking thoughtful partnership, Camille brings energy, clarity, and heart to every project.

Follow Me on Instagram